The Porthos and Aramis CCS projects invite qualified and experienced laboratories to submit a technical and commercial proposal for the preparation, execution, analysis and reporting of a programme of non-pure CO2 corrosion rate tests.
The proposal shall comply with this document; its appendices and all clarifications issued during the tender period. Where this document mentions ‘Porthos’ or ‘Aramis’ it can be read as ‘Porthos and Aramis’.
Description of Porthos
Porthos is developing an infrastructure to collect and transport CO2 from the industry in Rotterdam harbor to store CO2 in depleted gas fields beneath the North Sea. The pipeline trajectory from the Botlek Area in Rotterdam to platform P18 is depicted in the figure.
Porthos aims to store approximately 37 million tons of CO2, which equates to around 2.5 million tons of CO2 annually for a duration of 15 years.
The final investment decision for Porthos was made in October 2023. The construction activities for Porthos commenced in 2024, with the system expected to be operational from 2026 onwards. The project is close to finalization of the detailed engineering phase, and the construction of the onshore pipeline has started.
Description of Aramis
The Aramis project utilizes depleted gas fields and potentially aquifers in the Dutch North Sea to establish an open-access CCS infrastructure for transport and storage, targeting hard to abate industrial emissions in the Netherlands and Europe. This part of the project provides the infrastructure to transport CO2 from the onshore terminal to an offshore platform, which is used as distribution hub (D-Hub).
Other parts of the project are provided by CO₂Next and Porthos, while the actual storage in the depleted offshore gas fields under the North Sea is performed by Shell and TotalEnergies as part of their offshore operations.
In the figure below an overview of the envisaged CCS infrastructure is given. The left panel illustrates the trunkline that transports the CO2 from the Maasvlakte to the offshore storage. The middle panels illustrate the Maasvlakte Hub with the Porthos compressor station and the CO₂Next Terminal. The right panel shows the platforms of TTE and Shell. The Porthos project captures CO₂ from local industry Rotterdam and transports it by means of a pipeline via a compressor station at the Maasvlakte to offshore storage in two depleted gas fields.
Detailing of services to be provided
The corrosion testing program aims to generate reliable data for assessing pipeline integrity and supporting future corrosion management.
The main objectives are to:
– Quantify mass-loss corrosion rates for agreed carbon-steel coupons (API 5L X65 pipeline steel) under defined CO₂ compositions and operating conditions.
– The first approach will focus on gas phase CO2, as surface reaction/corrosion initiation has been observed from previous tests.
– Assess effects of impurities, methanol, water, temperature, pressure, and exposure duration on Coupon Corrosion.
– Identify and report uniform or localized corrosion, deposits, and reaction products.
Technical Scope Objective
The purpose of this program is to generate reliable corrosion data for carbon steel exposed to CO₂ streams containing impurities representative of the Porthos and Aramis value chains.
The work will support the technical basis for CO₂ specification development by improving understanding of corrosion initiation and corrosion rates under relevant operating conditions.
The Supplier shall engineer, prepare, execute, analyze and report on corrosion tests using agreed CO₂ compositions, impurity combinations, pressures, temperatures and exposure durations.
Basis of Test Program
The anticipated program comprises of twenty (20) corrosion experiments. The preliminary conditions and impurity combinations for first 12 tests are defined in Annex A. Final values will be agreed during the test-readiness phase.
More tests may follow which their matrix will be defined through the project.
Testing may include dense-phase and liquid/cryogenic CO2 conditions; bidder shall advise on any limitation on testing these conditions.
Test Media and Impurities
# Parameter Minimum requirement
1 Main CO2 Document source, purity and relevant background impurities (i.e. research grade 5.5 or higher)
2 H2O Controlled addition; state generation method and verification.
3 H2S Certified stock mixtures or equivalent traceable preparation.
4 SO2 Certified stock mixtures or equivalent traceable preparation.
5 NO2 Certified stock mixtures or equivalent traceable preparation.
6 O2 Certified stock mixtures or equivalent traceable preparation.
7 Methanol Controlled addition where specified; prevent unintended liquid carry-over.
8 Other impurities Controlled addition of impurities specified in Aramis CO2 specification where specified1.
Note 1: Most tests are limited to 4 or 6 components specified in the above table.
Corrosion Coupons
– Material: API 5L X65 pipeline steel
– Minimum three replicate exposed coupons per test, plus agreed blanks and archive coupons.
– Dimensions, orientation, surface area, machining direction and location in the vessel shall be documented.
– Surface preparation shall use an agreed final finish, normally #1000 grit, applied consistently.
– Each coupon shall have a unique permanent identifier that does not affect exposed surface measurements.
– Pre-exposure photographs, dimensions, area and mass shall be recorded.
Coupon Handling and Mass-Loss Method
Coupon preparation, post-test handling and chemical stripping shall follow Annex B.
Examinations and Analyses
# Activity Requirement
1 Visual examination Photograph vessel, deposits and coupons before and after cleaning. Record colour, distribution and visible local attack.
2 Mass loss Report original mass, cleaned mass, blank loss, exposed area, exposure time and corrosion rate for each coupon.
3 SEM/EDS Perform on selected coupons or deposits when requested. Retain chain of custody and mark analysed locations.
4 Chemical analysis Water wash of the autoclave hosting coupons.
5 Localised corrosion Where indicated, assess pit depth or morphology using an agreed method.
6 Archive samples Preserve agreed coupons, deposits and liquid samples for minimum of five years as explained in 1.4.13, and shall only be disposed after written agreement of Company.
7 Gas composition Continuous Analysis the composition of the CO2/impurity mixture downstream of the coupons to
1. look for reaction products and (if these are present)
2. identify them (via FTIR, GC, or equivalent)
Data Quality and Uncertainty
Supplier shall:
– Identify detection and quantification limits for analytical methods.
– Report target, set point and achieved conditions separately.
– Explain deviations, excursions, leaks, dosing instability, phase changes or contamination and assess their impact.
– Report and explain variability between replicate coupons and confidence in the test average.
– Include unsuccessful or anomalous tests in the reporting and clearly identify data considered unsuitable.
Test Procedure
Supplier shall develop and submit a detailed test procedure for Company approval prior to commencement of testing.
The procedure shall describe all activities required for preparation, execution, monitoring, examination and reporting of the corrosion tests.
As a minimum, the procedure shall include:
1. Test specimen preparation, dimensions, material certification and surface finish.
2. Test matrix, test conditions and exposure durations.
3. CO₂ composition and impurity introduction methodology.
4. Test corrosion cell configuration and operating procedures.
5. Monitoring, sampling and analytical methods.
6. Corrosion assessment methods, including mass loss, visual examination and surface analyses.
7. Quality assurance and quality control requirements.
8. Data recording, calculation methods and reporting format.
9. Health, safety and environmental considerations.
Any deviation from the approved procedure shall be subject to prior Company approval.
Experiment Milestones
# Milestone By Timing / status
1 Request supplier for a specific test Company Four (4) weeks before test starts
2 Detailed test procedure and final matrix including test readiness package Supplier Two (2) weeks before test starts
3 Brief preliminary results and key observations for each test Supplier Within one (1) week after test completion
4 Raw data package and photographs for each test Supplier Within one (1) week after test completion
5 Individual report per test for review by Company Supplier Within three (3) weeks after completion of each test
6 Final signed report and editable source files Supplier Within two (2) weeks after step 5 completed.
Minimum Report Content
The Report shall deliver a functional answer to Company’s needs; as a minimum reports by supplier shall contain:
1. Executive summary and test objective.
2. References, definitions and deviations from the approved procedure.
3. Description and photographs of facility, Process Flow Diagram (PFD), wet materials and coupon arrangement.
4. Coupon material certificates, preparation, dimensions, area and initial mass.
5. Target and achieved test conditions with time trends.
6. Impurity source, stock composition, dosing calculations and verification.
7. Observations during start-up, exposure, shut-in and termination.
8. Photographs and analysis of deposits and coupon surfaces.
9. Mass-loss table, blank correction, corrosion-rate calculations and replicate statistics.
10. Data quality, uncertainty, limitations and relevance to project conditions.
11. Conclusions, recommendations and proposed follow-up work.
12. Appendices containing raw data, calibration records and calculation sheets.
Document Requirements
Documentation by Supplier shall comply with the following requirements.
– Documents shall use English, SI/metric units and ppm-mol unless otherwise agreed.
– Final reports shall be provided in searchable PDF and editable Word format.
– Raw data shall be provided in Excel or CSV with clear units, timestamps and tag descriptions.
– Photographs shall be provided at original resolution / RAW format with traceable filenames.
– All deliverables shall carry document number, revision, status, date and approval signatures.
Intellectual Property and Data Ownership
Company shall own perpetual right to use, all project-specific test data, raw measurements, calculations, photographs, findings and reports for the Porthos and Aramis value chain and related project purposes. Publication or external disclosure requires prior written Company approval.
Records and Retention
The supplier shall retain controlled records, raw data and agreed physical samples for at least five (5) years after final acceptance, unless another period is specified in the contract. Records shall remain retrievable and protected against unauthorised modification. No data shall be removed unless agreed to this in writing by Company.
Preliminary Test Matrix
The matrix below is a tender basis and shall be completed or revised before tests execution.
Test Phase P (bar) T (°C) Duration Impurity Content (ppm-mol) Other / objective H2O H2S SO2 NO2 O2
CT-01 Gas [TBC]1 [TBC]2 10 d 50 – – 20 20 +100 ppm Methanol
CT-02 Gas [TBC]1 [TBC]2 10 d 20 – – 2.5 20 +100ppm MeOH @20 °C
CT-03 Gas Repetition of CT-02
CT-04 Gas [TBC]1 [TBC]2 10 d 20 – – 2.5 20 +100ppm MeOH 4 °C with and without after treatment
CT-05 Gas [TBC]1 [TBC]2 10 d 20 – – 2.5 20 Nox + 0ppm MeOH @20 °C
CT-06 Gas Repetition of CT-05
CT-07 Gas [TBC]1 [TBC]2 10 d 20 – – 2.5 20 Nox + 620ppm MeOH @20 or 4°C
CT-08 Gas Repetition of CT-07
CT-09 Gas [TBC]1 [TBC]2 10 d 20 0.5 3 2.5 20 Full composition, 100ppm MeOH @20 °C
CT-10 Gas [TBC]1 [TBC]2 10 d 20 0.5 3 2.5 20 Full Composition, 100ppm MeOH @ 4 °C
CT-11 Gas [TBC]1 [TBC]2 10 d 20 – – 2.5 20 +0ppm MeOH 20 °C at 40 °C
CT-12 Gas [TBC]1 [TBC]2 10 d 20 – – 2.5 20 2.5ppm NOx+ 100ppm MeOH 20 °C at 40 °C
1- Pressure up to 30bar for Gas phase and up to 100bar for Dense phase.
2- Temperatures from -30 to +40°C.
Mass-Loss Procedure
Procedure for mass loss measurement of carbon steel corrosion coupons using Clarke’s solution (inhibited hydrochloric acid)
– Prepare, mark, wash the coupon with distilled water (2 seconds) and IPA (20 seconds) and dry each corrosion coupon in gentle air stream
– Record the unexposed weight of each coupon.1
– Store the dried coupons in a desiccator or warm oven.
– Expose the coupons according to the experimental procedure.
– Terminate the experiment by flushing the autoclave with dry CO2 (at test pressure) for at least 30 minutes.
– Depressurize the autoclave (gently).
– Take the coupons out of the autoclave
– As fast as possible: Remove any residue/dropout by wiping with lint free cloth.
– As fast as possible: Submerge the coupon in distilled water for 2 seconds.
– As fast as possible: Submerge the coupon in isopropanol for at least 20 seconds & dry in gentle air stream.
– In case of SEM/EDX or other coupon analyses (besides weight loss) to investigate the deposits composition and structure, they must be executed before chemical stripping. If the composition (EDS) of products is of interest, the coupons to be investigated should only be submerged in isopropanol (no submerging in water and no wiping).
– For chemical stripping (removal of the corrosion products), immerse the coupon in Clarke’s Solution at room temperature according to ASTM G1; table A1.12 for 1-5 minutes for light to moderate corrosion and 15-25 minutes for heavy rust/severe deposits. Immersion time to be checked by 1-minute intervals. (Use the fume hood). Other chemical stripping solutions are described in ASTM G1; table A1.1 and can be used after consultation. Important is to “Subject a pre-weighed blank that was not exposed to the corrodent to the cleaning process to ensure that mass loss from cleaning is not significant”.
– Immerse the coupon in distilled water to stop the acid reaction. 10 seconds is sufficient but make sure to use enough water to sufficiently dilute any traces of acid.
– Submerge the coupon in isopropanol for 20 seconds & dry in gentle air stream.
– Weight the coupon +/- 0.1 mg.
1 It is generally recommended to also weigh a calibration weight every time a coupon is weighed. Any intermittent drift of the scale can then be corrected for. The calibration weight should be as close as possible to the actual coupon weight. Use the same scale and the same calibration weight every time.
2 ASTM G1: Clarke’s solution is made by mixing 1000 mL hydrochloric acid (HCl, sp gr 1.19) with 20 g antimony trioxide (Sb2O3) and 50 g stannous chloride (SnCl2). IFE replaced the 20 grams Sb2O3 with 30 gram of SbCL3 for safety reasons.
Health, Safety and environment
Porthos places great importance on the Health and Safety of the employees of Porthos and its contractors and subcontractors. Tenderer shall perform the work in such a manner that the health and safety of all personnel is ensured during the performance of the work and fully in line with the contract including the Porthos General terms and conditions (Annex D1), Code of Conduct for Suppliers (Annex D2) and the Porthos HSE Policy (Annex D3).
– The Tenderer shall declare that existing facilities and equipment can perform all specified corrosion tests within the required pressure, temperature and CO₂ composition ranges.
– The Tenderer shall demonstrate capability to perform the required analyses, including visual examination, mass-loss measurement, SEM/EDS, chemical analysis and gas composition analysis.
– The Tenderer shall provide one (1) reference demonstrating successful completion of a comparable CO₂ corrosion testing project within the previous three (3) years.
– The Tenderer shall hold valid ISO/IEC 17025 accreditation covering the proposed testing activities and valid ISO 9001 and ISO 14001 certifications.
– Tenderer shall demonstrate the capability to commence the first test within six (6) weeks of Contract Award and complete and report eight (8) corrosion tests within four (4) months of Contract Award.
– Test procedure, including specimen preparation, exposure, examination, analysis and acceptance checks.
– Quality assurance and quality control measures applied during testing and analysis.
– Procedures for equipment calibration, measurement traceability, sample handling and preservation.
– Proposed report structure, deliverables and technical review process.
– Expaination on how the target CO₂ composition and impurity levels will be prepared, controlled, and verified during the test and shall identify any technical limitation on the number of impurities that can be dosed simultaneously, exposure duration, pressure, temperature, residence time or analytical capability.
– Tenderer Provide calibration status, instrument range, resolution and uncertainty for all measurements including pressure, temperature, flow, mass and composition.